Utility Interconnection Process: From Application to Permission to Operate PTO

utilities interconnection planning

The solutions are categorized by time scale and deployment level to help stakeholders identify those that best meet regional needs. However, interconnection processes https://suscinio.info/3-tips-from-someone-with-experience-6/ must accommodate a growing volume of interconnection requests and adapt to local markets with specific needs. In the latest decision, FERC approved PJM’s proposal for defining large loads and its plan to create a large load “registry” that would include a facility’s location, ramp schedule, capacity supply and other details. The Transcend Utility Interconnection Hub simplifies the interconnection process by providing an automated platform that ensures developers submit fully compliant collector substation designs from the start.

  • It provides stakeholders with strategies to improve interconnection processes to meet growing demand for more generators, storage systems, large loads, and hybrid facilities on distribution networks.
  • FERC, utilities, regional grid operators, generators and other stakeholders are working to address the long study periods in the interconnection queue through revisions to federal rules and regional and utility interconnection procedures.
  • In the last five years, interconnection queues — generators waiting to have their proposed projects studied to see if grid upgrades are required to bring them online — have surged.
  • Embracing these technological advancements will ensure that grid interconnection planning remains a dynamic and resilient process, capable of meeting the demands of an increasingly complex energy landscape.
  • “For the first time, SPP’s interconnection customers can know what they will pay to connect to the grid before entering the interconnection queue, turning the page on never-ending studies, restudies, and cost uncertainty that ultimately lead to generators withdrawing,” Rosner said.

About 2,000 GW of mostly renewable generation and energy storage are in interconnection queues across the United States, with recent projects taking five years on average to complete the interconnection process, according to Becca Jones-Albertus, director of DOE’s Solar Energy Technologies Office. Other reforms aim to limit the interconnection queue to viable projects, motivate utilities and RTOs to meet study deadlines, and incorporate new transmission technologies in the study process. A national scorecard that provides a detailed assessment of state-level interconnection policies, assigning grades based on criteria such as universal applicability, minimal application costs, reasonable timelines, and transparent technical criteria. Interconnection standards are typically established by state-level public utility commissions (PUCs) and mandate how utilities must connect renewable energy systems to the electric grid, with a parallel permitting process required by local jurisdictions to ensure that systems are installed safely.

  • However, on September 22, representatives and stakeholders from all thirteen PJM states, including Pennsylvania Governor Josh Shapiro, discussed novel ways to address this challenge at the Summit on the State of PJM Interconnection, highlighting an appetite to find solutions to this issue.
  • Rapid and accelerating load growth, backlogged interconnection queues, limited regional/interregional transmission buildout, ongoing supply chain issues and increasingly frequent extreme weather events are exacerbating reliability concerns and raising electricity bills for consumers.
  • These can include building new transmission lines, rebuilding transmission lines to be higher voltage, or reconductoring of existing lines, as well as deploying new equipment at substations or onto other parts of the system to ensure reliability.
  • SPP says the CPP “will proactively ensure that the right, and most optimal, transmission upgrades are built at the right time and that costs are shared between generation and load based on roughly commensurate benefits to each.”
  • FERC Order No. 2023 requires transmission providers to use first-ready, first-served cluster studies and meet study deadlines for generator interconnection, while ERCOT, NYISO, and SPP are also developing new interconnection processes for large loads.

Grid https://photoshopalternative.com/2025/04/14/5-lessons-learned-3/ interconnection planning stands at the confluence of technology, analytics, and engineering expertise. As technology continues to evolve, several trends are set to redefine grid interconnection planning. Engineers also engaged with stakeholders through collaborative tools such as Team Chat to ensure all systems and protocols were clearly understood before deployment. Tools that provide a comprehensive Overall AI Report help identify potential synchronization issues and allow engineers to craft well-informed solutions that maximize grid resilience. Interconnection costs are generally allocated by having the project owner cover direct connection costs, including equipment and upgrades specific to their project. FERC on Thursday extended the original deadline for transmission operators to file their interconnection compliance plans for review by the agency by about four months to April 3.

utilities interconnection planning

How to get started

SPP says the CPP “will proactively ensure that the right, and most optimal, transmission upgrades are built at the right time and that costs are shared between generation and load based on roughly commensurate benefits to each.” However, on September 22, representatives and stakeholders from all thirteen PJM states, including Pennsylvania Governor Josh Shapiro, discussed novel ways to address this challenge at the Summit on the State of PJM Interconnection, highlighting an appetite to find solutions to this issue. Rapid and accelerating load growth, backlogged interconnection queues, limited regional/interregional transmission buildout, ongoing supply chain issues and increasingly frequent extreme weather events are exacerbating reliability concerns and raising electricity bills for consumers. FERC Order No. 2023 requires transmission providers to use first-ready, first-served cluster studies and meet study deadlines for generator interconnection, while ERCOT, NYISO, and SPP are also developing new interconnection processes for large loads. "Duke Energy maintains one of the largest utility grids in the United States, and our engineers must complete a higher volume of increasingly complex studies as demand for generation and load grows," said John Pressley, Managing Director of Digital Strategy and Engineering at Duke Energy.

utilities interconnection planning

What is an Integrated Resource Plan (IRP) and how does it guide long-term energy planning for utilities?

These can include building new transmission lines, rebuilding transmission lines to be higher voltage, or reconductoring of existing lines, as well as deploying new equipment at substations or onto other parts of the system to ensure reliability. The existing framework treats transmission planning and generator interconnection as separate, siloed processes — leading to delays, repeated studies, cost uncertainty, and an increasingly unworkable interconnection queue. The vehicle for this signal was FERC’s approval of Southwest Power Pool’s (SPP) Consolidated Planning Process (CPP), a sweeping overhaul of interconnection and transmission planning that Commissioners described as a potential national template for addressing interconnection backlogs. SPP has about 105 GW in its generation interconnection queue, including about 32 GW of thermal generation, 22 GW of battery storage and 21 GW of solar, according to the grid operator, which runs the electric system and wholesale power markets in 14 states from New Mexico to North Dakota.

utilities interconnection planning

  • Grid interconnection planning stands at the confluence of technology, analytics, and engineering expertise.
  • The existing framework treats transmission planning and generator interconnection as separate, siloed processes — leading to delays, repeated studies, cost uncertainty, and an increasingly unworkable interconnection queue.
  • Engineers also engaged with stakeholders through collaborative tools such as Team Chat to ensure all systems and protocols were clearly understood before deployment.
  • SPP has about 105 GW in its generation interconnection queue, including about 32 GW of thermal generation, 22 GW of battery storage and 21 GW of solar, according to the grid operator, which runs the electric system and wholesale power markets in 14 states from New Mexico to North Dakota.
  • The vehicle for this signal was FERC’s approval of Southwest Power Pool’s (SPP) Consolidated Planning Process (CPP), a sweeping overhaul of interconnection and transmission planning that Commissioners described as a potential national template for addressing interconnection backlogs.

Actual timelines vary based on utility workload, local grid capacity, and how accurate and complete your submission is. Unlike residential systems, commercial solar interconnection involves more technical review, detailed grid impact studies, and often, utility-specific engineering requirements. Interconnection processes involve complex regulatory structures, specific jurisdictional authorities, and numerous stakeholders. Through the GRID-C framework, SPP will set a per-megawatt charge for interconnecting customers that reflects their share of system network upgrade costs, with those revenues credited to load paying for the same upgrades under SPP’s highway/byway cost allocation methodology. “This landmark change in SPP’s long-term planning and cost allocation processes was unopposed in SPP’s stakeholder process — a nearly unprecedented feat in SPP’s diverse stakeholder process for a proposal that marks a sea change in transmission planning and cost allocation,” SPP said. Working with its stakeholders, SPP started considering broad changes to its transmission planning process in 2020.

Resources and Tools

It provides stakeholders with strategies to improve interconnection processes to meet growing demand for more generators, storage systems, large loads, and hybrid facilities on distribution networks. FERC, utilities, regional grid operators, generators and other stakeholders are working to address the long study periods in the interconnection queue through revisions to federal rules and regional and utility interconnection procedures. “For the first time, SPP’s interconnection customers can know what they will pay to connect to the grid before entering the interconnection queue, turning the page on never-ending studies, restudies, and cost uncertainty that ultimately lead to generators withdrawing,” Rosner said. Embracing these technological advancements will ensure that grid interconnection planning remains a dynamic and resilient process, capable of meeting the demands of an increasingly complex energy landscape. In the last five years, interconnection queues — generators waiting to have their proposed projects studied to see if grid upgrades are required to bring them online — have surged. That’s why DOE and the national labs are partnering with utilities, grid operators, state and local governments, energy industry groups, non-profits, and others to share data, develop roadmaps, and facilitate new solutions to improve interconnection procedures.